www.rkiinstruments.comHydrogen SulfideBeacon 200 Rig MonitorOperator’s ManualPart Number: 71-0236RKRevision: BReleased: 9/30/14
5 • Beacon 200 Rig Monitor Operator’s ManualExternal DescriptionThis section describes the housing and all external components of the Beacon 200 Rig
Beacon 200 Rig Monitor Operator’s Manual • 6H2S Detector Junction Boxes and CablesEach of the two H2S detectors consists of a junction box with a mou
7 • Beacon 200 Rig Monitor Operator’s Manualthere is enough room to perform a calibration. A cover on the front of the junction box allows access to
Beacon 200 Rig Monitor Operator’s Manual • 8Internal DescriptionThis section describes the internal components of the Rig Monitor.Display Printed Cir
9 • Beacon 200 Rig Monitor Operator’s ManualStatus LightsThe Rig Monitor includes four status lights that indicate the current status of the monitor.
Beacon 200 Rig Monitor Operator’s Manual • 10Main PCBThe main PCB is mounted inside the housing. The power supply mounting plate is mounted to the ma
11 • Beacon 200 Rig Monitor Operator’s Manual• DC In Terminal Strip. The DC in terminal strip is a 3-point terminal strip located above the controlle
Beacon 200 Rig Monitor Operator’s Manual • 12NOTE: The alarm 2 channel relays may be set to operate as individual channel fail relays. See “Configure
13 • Beacon 200 Rig Monitor Operator’s ManualChapter 3: Installation and Start UpOverviewThis chapter describes procedures to mount the Beacon 200 Ri
Beacon 200 Rig Monitor Operator’s Manual • 14 1. Select the mounting site. When you select the mounting site consider the following factors:• Can the
Beacon 200 Rig Monitor Operator’s ManualWARNINGRead and understand this instruction manual before operating instrument. Improper use of the rig monit
15 • Beacon 200 Rig Monitor Operator’s Manual• Are the display screen and status lights visible? 2. Close and latch the housing door. 3. Position the
Beacon 200 Rig Monitor Operator’s Manual • 16Wiring the Beacon 200 Rig MonitorThe detector leads, junction box connections, power cable wiring, and s
17 • Beacon 200 Rig Monitor Operator’s ManualWARNING: Make all connections to the Beacon 200 Rig Monitor before you connect the DC power source. Befo
Beacon 200 Rig Monitor Operator’s Manual • 18bushing. 4. Guide the wiring of the external alarm device through the new conduit hub on the bottom of t
19 • Beacon 200 Rig Monitor Operator’s Manual 5. Connect the wires form the recording device to the recorder output terminals as shown in Figure 10.S
Beacon 200 Rig Monitor Operator’s Manual • 20Chapter 4: OperationOverviewThis chapter describes the Beacon 200 Rig Monitor in normal operation. This
21 • Beacon 200 Rig Monitor Operator’s ManualRecorder Output OperationThe output at the recorder output terminals is a 4 - 20 mA signal for each acti
Beacon 200 Rig Monitor Operator’s Manual • 22Alarm IndicationsThis section describes the Rig Monitor in alarm 1, alarm 2, and fail conditions and sug
23 • Beacon 200 Rig Monitor Operator’s ManualNOTE: You can select normally energized (NE) or normally de-energized (NDE) channel relay settings in th
Beacon 200 Rig Monitor Operator’s Manual • 24Alarm 2 ConditionThis section describes the audible and visual indications for an alarm 2 condition and
Beacon 200 Rig Monitor Operator’s ManualProduct WarrantyRKI Instruments, Inc. warrants gas alarm equipment sold by us to be free from defects in mate
25 • Beacon 200 Rig Monitor Operator’s Manual• The display reading is -10% of full scale or lower.• The Rig Monitor or detector head is malfunctionin
Beacon 200 Rig Monitor Operator’s Manual • 26Viewing & Resetting Min/Max ReadingsThe Reset switch may be used to view and reset the minimum and m
27 • Beacon 200 Rig Monitor Operator’s ManualChapter 5: Channel Control and Setup ProgramOverviewThe Channel Control & Setup Program allows viewi
Beacon 200 Rig Monitor Operator’s Manual • 28Enable/Disable Channel(s) Menu 1. From normal operation, simultaneously press and hold the ESCAPE and EN
29 • Beacon 200 Rig Monitor Operator’s ManualConfigure Channel Settings MenuThis section describes how to view and change channel parameters for the
Beacon 200 Rig Monitor Operator’s Manual • 30 10.Press the UP/YES button to save the configuration. The screen will then return to the Channel Contro
31 • Beacon 200 Rig Monitor Operator’s ManualView System Information MenuThe View System Information Menu consists of only one display screen which i
Beacon 200 Rig Monitor Operator’s Manual • 32Chapter 6: MaintenanceOverviewThis chapter describes use of the Calibration Program and corrective maint
33 • Beacon 200 Rig Monitor Operator’s ManualNOTE: The following procedure assumes that the target gas is present in a high enough concentration to a
Beacon 200 Rig Monitor Operator’s Manual • 34NOTE: While in the Calibration Program, the alarm status of the Beacon 200 Rig Monitor will be locked in
Beacon 200 Rig Monitor Operator’s ManualTable of ContentsChapter 1: Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
35 • Beacon 200 Rig Monitor Operator’s Manual 4. Screw the fixed flow regulator into the zero air calibration cylinder. 5. Use the calibration kit sa
Beacon 200 Rig Monitor Operator’s Manual • 36If you press the DOWN/NO button, the span of channel 1 will continue if you selected it or if you did no
37 • Beacon 200 Rig Monitor Operator’s ManualIf the Rig Monitor is able to successfully make the calibration adjustment, it will display the message
Beacon 200 Rig Monitor Operator’s Manual • 38 4. Grasp the top and bottom of the strobe/horn and push up and out in order to remove the cover. 5. Tur
39 • Beacon 200 Rig Monitor Operator’s Manualfactory setting is 2. 7. Turn the Audio Select switch so that the selection arrow is pointing to the des
Beacon 200 Rig Monitor Operator’s Manual • 40 10.Close and secure the housing door.Replacing the Plug-In H2S Sensor 1. Open the housing door of the R
41 • Beacon 200 Rig Monitor Operator’s ManualVDC battery. 3. Remove the H2S detector junction box cover. 4. Disconnect the detector leads from the te
Beacon 200 Rig Monitor Operator’s Manual • 42MonthlyThis procedure describes a test to verify that the H2S detectors respond properly to hydrogen sul
43 • Beacon 200 Rig Monitor Operator’s ManualNOTE: If the reading is not within ± 20% of the correct response reading, calibrate the detector as desc
Beacon 200 Rig Monitor Operator’s Manual • 44Flickering Display• The display readings flicker often.• The Beacon 200 is experiencing false readings d
Beacon 200 Rig Monitor Operator’s ManualChapter 6: Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
45 • Beacon 200 Rig Monitor Operator’s ManualSlow or No Response/Difficult or Unable to Calibrate• Rig Monitor responds slowly or does not respond to
Beacon 200 Rig Monitor Operator’s Manual • 46Parts ListTable 10 lists the part numbers and descriptions for replacement parts and accessories offered
1 • Beacon 200 Rig Monitor Operator’s ManualChapter 1: IntroductionOverviewThis chapter briefly describes the Beacon 200 Rig Monitor. This chapter al
Beacon 200 Rig Monitor Operator’s Manual • 2About this ManualThe Beacon 200 Gas Monitor Operator’s Manual uses the following conventions for notes, c
3 • Beacon 200 Rig Monitor Operator’s ManualSpecificationsTable 1 lists specifications for the Beacon 200 Rig Monitor. WARNING: When using the Beacon
Beacon 200 Rig Monitor Operator’s Manual • 4Chapter 2: DescriptionOverviewThis chapter describes external and internal components of the Beacon 200 R